Tata's Agratas loses second builder at UK gigafactory, says it is still on track

The 40 GWh Somerset plant meant for Jaguar Land Rover has lost two contractors in five months, while its sister plant at Sanand moves on with its own deadline.

Tata's Agratas loses second builder at UK gigafactory, says it is still on track
Cover: Moto365 Club, with a photo from Burnham-On-Sea.com

TSL took charge of building Agratas' battery cell factory in Somerset in June 2026. Five months later it is leaving too. It is the second main contractor to walk away from the Tata Group's flagship UK battery project.

The Guardian first reported the exit on 23 November, citing three unnamed sources, and electrive picked it up two days later. Agratas had already let go of Sir Robert McAlpine, the original contractor. TSL then stepped in to manage construction, and has now decided to step down. It will leave the site within two to three months. According to electrive, the reported cause is disagreement over timeline and cost.

This matters in India because the same company is building India's other big cell bet. Agratas, Tata's battery arm, is putting up a cell plant at Sanand in Gujarat. Its first phase is planned at 20 GWh a year, with production due to begin in 2027, Autocar Professional reported in April. The Somerset factory is the larger twin and the one with the harder deadline. How Agratas handles a stalled build in England is the clearest test yet of whether it can deliver cells on time for Tata's cars at home.

Two dates, one factory

The numbers on the Bridgwater site are large. Electrive puts the plan at 40 GWh a year, an investment of £5.2 billion, about 4,000 jobs and a £380 million pledge from the British government. The project was announced in February 2024. Production was first expected in 2026.

Since then the date has moved, and the reports do not agree on where it now sits. Burnham-On-Sea.com, the local news site, reported on 25 November that Agratas now expects the factory to open at the end of 2027, with 1,500 operational jobs that year. Electrive says the start of production is slated for January 2028.

How it unfolded

How the Agratas Somerset cell plant timeline has moved

  1. February 2024Agratas announces the 40 GWh Somerset plant. Production first expected in 2026
  2. June 2026TSL takes over construction management after Sir Robert McAlpine is dismissed
  3. 23 November 2026The Guardian reports TSL will step down as main contractor
  4. January 2028Start of production now slated, per electrive

Source: electrivemoto365.club

Agratas insists nothing is broken. A spokesperson told The Guardian, "We are on track to meet our customer requirements." Speaking to Burnham-On-Sea.com, the company called the site "a large and complex industrialisation project". It said it does not need to name a replacement for TSL, whose role it describes as exterior works. NG Bailey, already on site, will handle the internal fit-out. Electrive reports that NG Bailey is being considered to take over construction management, and that no successor has been confirmed.

What is already built gives Agratas some cover. The building shell is largely complete, electrive says, and National Grid has begun work on a substation. About 2,000 people have worked on the site this year, according to Burnham-On-Sea.com.

The customer who can wait

The cells from Bridgwater are meant mainly for Jaguar Land Rover, another Tata company. Here the delay has already been planned around. Citing The Guardian, electrive reports that JLR has lined up interim battery supply from other makers, so its electric Land Rover and Jaguar models are not at risk. The catch is that the first of those vehicles will not use UK-made cells.

Electrive compares the project with Britishvolt. That company failed early, partly because it had no binding orders, and its old site in north-east England is being turned into an AI data centre. Agratas has a buyer in its own group. What it does not have yet is a main builder in England.

At Sanand the work is further along. In March, Agratas said civil construction there was nearing completion and its focus had shifted to installing equipment and training staff. Deepak Khare, its Vice President of Manufacturing Operations, described the job as "establishing the systems, processes and capabilities required for state-of-the-art cell production". The company's news page now reports that the first process equipment has arrived at the plant's E Zone.

Both factories are now aimed at roughly the same window, late 2027 into early 2028. Only one of them still has to find someone to finish the building.

Sources

  1. electrive: Tata Group's British battery cell factory faces delays electrive.com
  2. Burnham-On-Sea.com: Agratas says Somerset gigafactory remains on track despite contractor stepping away burnham-on-sea.com
  3. Autocar Professional: Agratas hits key construction milestone at Sanand battery facility autocarpro.in
  4. Agratas: Agratas progresses towards operational readiness at Sanand agratas.com
  5. Agratas news agratas.com